10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The PRINCE2-P exam has 56 questions and runs 2 hours 30 minutes.
These 10 free PRINCE2-P questions are organized by exam domain, so you can see how each part of the PRINCE2 Practitioner (PRINCE2-P) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Practices 51% of exam
Question 1
Six months into a two-year project to build a new customer booking platform, a competitor releases a free equivalent that removes most of the forecast revenue benefit. The project is currently within all of its stage tolerances and the team is performing well. The project executive recommends closing the project immediately. Is this recommendation appropriate?
Show answer & explanation
Correct answer: A - Yes, because a project should be stopped once its business justification is no longer valid
Question 2
A four-week internal project has a team of three. To reduce management overhead the project manager proposes to: use the organisation's existing 'steering group' terminology in place of 'project board'; combine the highlight report and the end stage report into one fortnightly update; and run the whole project as a single management stage. Which statement about this proposal is correct?
Show answer & explanation
Correct answer: D - It is not appropriate, because a PRINCE2 project needs an initiation stage plus at least one further stage
Domain 2: Processes 30% of exam
Question 3
Staff in the affected department tell the project manager that they are anxious about how the new operating model will change their day-to-day roles, and several say they are unlikely to use the new system once it is delivered. Through which of the following should the project manager primarily address this?
Show answer & explanation
Correct answer: D - The change management approach, which defines how people will be moved to the target state
Question 4
A project delivers a new staff scheduling system on time, within budget, and meeting every one of its quality criteria. Six months after handover, most staff have reverted to the previous manual process. Which statement best describes this position?
Show answer & explanation
Correct answer: B - The project delivered its outputs, but without adoption the intended outcome and benefits are not achieved
Domain 3: Principles 10% of exam
Question 5
A project to replace a delivery fleet has agreed a measurable target to cut fleet emissions by 30%, with a permitted variance of plus or minus 5%. Which statement about this target is correct?
Show answer & explanation
Correct answer: A - It is a sustainability target and, like the other project performance targets, it carries tolerance
Question 6
The project board is short of available people. The project executive suggests that the project manager should also carry out user assurance, on the grounds that the project manager knows the user community best. Is this appropriate?
Show answer & explanation
Correct answer: C - No, because project assurance must remain independent of the project manager
Question 7
The project will be delivered by two competing suppliers working in parallel, with payment linked to milestone acceptance. In which management product should this arrangement be documented?
Show answer & explanation
Correct answer: D - The commercial management approach, within the project initiation documentation
Question 8
The project manager has written the project product description and has just agreed the product breakdown structure with the team. Which product-based planning step should be carried out NEXT?
Show answer & explanation
Correct answer: B - Write the product descriptions
Question 9
A project will deliver a new website, a mobile app and a staff training package. The senior user states that the website's public pages must load in under two seconds on a standard mobile connection. Where should this specific requirement be recorded?
Show answer & explanation
Correct answer: C - In the product description for the website, as one of its quality criteria
Question 10
At a checkpoint meeting the team manager reports that the specialist contractor engaged to install the network hardware has entered administration and has stopped work. How should the project manager treat this?
Show answer & explanation
Correct answer: A - As an issue, because the event has already occurred